Wednesday, January 26, 2011

furnaces are being prepared for hookup in the spring

door hardware is being put on

Thursday, January 13, 2011

prepping the floors
vinyl flooring in one unit

still installing the ductwork

Wednesday, January 5, 2011

bathroom tiling is done
plumbing is coming along

just about the end of the cupboards
counter tops and flooring yet to be done